190 m² of clinker brick, three masons and less than two weeks — a façade done fast and clean.
Project challenges
01
Tight deadline
The client was aiming for the fastest possible completion — without losing quality.
02
Small team
Only three masons for the whole scope — every stage had to run without downtime.
03
Clean clinker brick
Facing masonry forgives no sloppiness — a level joint on every course.
Our solutions
How did you fit into 12 days?
A simple, well-calculated façade and refined processes: preparation, masonry and pointing ran without waiting.
Who worked on the site?
A crew of three experienced masons — enough for such a scope with coordinated work.
What was the result?
A clean, predictable façade with no delays or complications — in 12 days.
Result
190 m² of façade delivered in 12 days — fast, clean, with no rework.
190m² of façade
12days
3masons
0reworks