200 m² of masonry with Porotherm and natural stone — starting with fixing the previous contractor's mistakes.
Project challenges
01
Predecessor's mistakes
The rear wall was off by 5–6 cm due to sloppy masonry by the previous company — the building's geometry was at risk.
02
No crane, by hand
All materials were fed by hand and the scaffolding was assembled by our own team — without external contractors.
03
Two materials, precision
Structural Porotherm masonry plus rubble masonry with natural stone — two different approaches on one project.
Our solutions
How did you correct the geometry?
We fully dismantled the rear wall, corrected the geometry and only then carried out the structural Porotherm masonry — strictly to specification.
How did you work without equipment?
Manual material feeding and our own scaffolding — the structural stage (2 storeys + garden walls) was completed in a month.
What was the outcome?
Corrected geometry, clean structural masonry and natural stone cladding — technical responsibility at every stage.
Result
Corrected building geometry, clean Porotherm masonry and natural stone cladding — 200 m² in two months.
200m² of masonry
2months
2crews
5–6 cmcorrected