700 m² of façade by two crews — a clean result in 1.5 months of work, despite downtime not on our side.
Project challenges
01
Downtime on the client's side
Work periodically stopped due to supply delays and the client's organisational pauses.
02
Stretched schedule
The timeline extended for reasons beyond our control.
03
Consistent quality
Despite the interruptions, the façade had to come out even and without rework.
Our solutions
How did you handle the downtime?
Two crews of three masons each delivered their part to a high standard and returned to rhythm as soon as the pauses were lifted.
How long did the actual work take?
Only 1.5 months of net working time — the rest were forced pauses.
What was the result?
A neat façade with no rework — even despite the external delays.
Result
A neat 700 m² façade with no rework — in 1.5 months of actual work, despite downtime not on our side.
700m² of façade
1,5months
2crews
0reworks